Net Present Value of a Forestry Project
< Prev
Next >

A sustainable forestry project is designed to yield a net profit of $10 million per year over 5 years. The net present value (NPV) of these cash flows is given by $$NPV = \sum_{t=0}^{4} \frac{10\,\text{million}}{(1+0.05)^t}$$ using a discount rate of 5%. What is the approximate NPV of the project?

A

Approximately $40 million.

B

Approximately $55 million.

C

Approximately $50 million.

D

Approximately $45.5 million.