Wind Turbine CO2 Offset Calculation

Mark
< Prev
Next >

A county has a goal to offset 52005200 tons of CO2 annually using wind energy. Each megawatt (MW) of installed wind capacity is expected to offset 26002600 tons of CO2 per year. If each wind turbine has a capacity of 0.5 MW0.5 \text{ MW}, how many turbines must be installed to meet the county’s goal?

A

8 turbines

B

4 turbines

C

2 turbines

D

10 turbines